| 5 | 1 | CWPPRA | Lake Borgne Shoreline Protection at Bayou Dupre | St. Bernard | $3566000.00 |
| 9 | 4 | CWPPRA | South Grand Chenier Hydrologic Restoration | Cameron | $6750000.00 |
| 15 | 2 | CIAP | Lake Lery Dedicated Dredging | St. Bernard | $29300000.00 |
| 17 | 1 | CWPPRA | Southern Chandeleur Island Back Barrier Marsh Creation | St. Bernard | |
| 18 | 3 | CWPPRA | Southwest Pass Hydrologic Restoration | Vermilion | $8890000.00 |
| 19 | 3 | CWPPRA | Bayou Terrebonne East Bank Hydrologic Restoration Project | Terrebonne | $2350000.00 |
| 20 | 3 | CWPPRA | Blue Hammock Bayou Hydrologic Restoration and Beneficial Use Project | Terrebonne | $6520000.00 |
| 27 | 2 | CWPPRA | Delta-Building Diversion North of Fort St. Phillip | Plaquemines | $6355000.00 |
| 29 | 2 | CWPPRA | Delta-Building Diversion at Benny's Bay 50000 cfs with Outfall Management | Plaquemines | $37613000.00 |
| 35 | 1 | CWPPRA | Bonnet Carre Sediment Trap (Shoreline Protection from Frenier to the La Branche Marsh Creation site) | St. Charles | $55815979.00 |
| 36 | 1 | CWPPRA | Beneficial Use of Dredged Material on Breton and Grand Gosier Islands | Plaquemines | $16245000.00 |
| 38 | 2 | CIAP | South Lake Salvador Shoreline Protection and Marsh Creation | Lafourche | $19389000.00 |
| 39 | 3 | CWPPRA | Shell Island Pass Marsh Creation | St. Mary | $3060000.00 |
| 40 | 3 | CIAP/Vermilion Parish | Shoreline Protection Chenier Au Tigre to Southwest Pass | Vermilion | $25100000.00 |
| 41 | 4 | CWPPRA | Pecan Island Freshwater Introduction Enlargement | Vermilion | $3206000.00 |
| 42 | 4 | CIAP | Grand Lake Shoreline Protection/Marsh Creation Superior Canal/ Mermentau River | Cameron | |
| 43 | | CWPPRA | Deep Hole Breakwaters | Plaquemines | $2485000.00 |
| 44 | | CWPPRA | Enhancing Salt Marsh Creation by Coupling Bay Bottom Terracing with Innovative SAV Plantings | Coastwide | $1642000.00 |
| 45 | | CWPPRA | Fiber Mat Demo for Erosion Control and SAV and Marsh Creation | Terrebonne | $1602000.00 |
| 57 | 3 | CWPPRA | South Lake Decade Atchafalaya Freshwater/Sediment Introduction | Terrebonne | $5000000.00 |
| 58 | 2 | CWPPRA | River Diversion (15000 cfs) Between Triumph and Venice | Plaquemines | $50000000.00 |
| 60 | 4 | CWPPRA | Little Pecan Bayou Hydrologic Restoration | Cameron | $15271778.00 |
| 64 | 1 | CIAP/Tangipahoa Parish | Tangipahoa/Pontchartrain Shoreline Protection | Tangipahoa | $5000000.00 |
| 65 | 2 | CWPPRA | Amoretta (City Price) Freshwater Diversion | Plaquemines | |
| 66 | 2 | CWPPRA | East Golden Meadow Terracing Project | Lafourche | $2327000.00 |
| 67 | 2 | CWPPRA | Grand Pierre Island Restoration | Plaquemines | $10000000.00 |
| 68 | 3 | CWPPRA | North Bully Camp Outfall Management | Lafourche | $5000000.00 |
| 69 | 3 | CIAP | Deer Island/East Pass Channel to Fourleague Bay | St. Mary | |
| 70 | 3 | CWPPRA | North Houma Navigational Channel Salinity Control Project | Terrebonne | |
| 71 | 4 | CWPPRA | Construction at Lighthouse Bayou | Cameron | $5000000.00 |
| 72 | 4 | CIAP/State & Vermilion Parish | Freshwater Bayou Canal Shoreline Stabilization and Hydrologic Restoration (Schooner Bayou to the GIWW) | Vermilion | $5000000.00 |
| 73 | 4 | CWPPRA | Restore Original Mermentau River | Cameron | $5000000.00 |
| 75 | 2 | Jefferson Parish Dept of Environmental Affairs | Wave Absorbers/Reef Zones in Barataria Bay | Jefferson | |
| 77 | 4 | Arabie Environmental Solutions, Inc. (AES) | South Fork of Black Bayou | Cameron | |
| 78 | 3 | Terrebonne Parish/USFWS | Repair Cuts in Bayou Chauvin Natural Levees | Terrebonne | |
| 79 | 3 | Terrebonne Parish/USFWS | Vegetative Plantings North Shore of Lost Lake | Terrebonne | |
| 80 | 3 | Terrebonne Parish/USFWS | Plug Canals along East Bank of Bayou Terrebonne | Terrebonne | |
| 81 | 3 | Terrebonne Parish/USFWS | Armor Sections of the HNC Spoil Banks | Terrebonne | |
| 83 | 3 | Terrebonne Parish/USFWS | Rebuild Minor's Canal Weir | Terrebonne | |
| 84 | 2 | Nature Conservancy | Des Allemands (Portfolio Site_N.C.) | St. John/St. Charles/Lafourche | |
| 85 | 1 | Nature Conservancy | Maurepas (Portfolio Site_N.C.) | Livingston/Ascension/St. John | |
| 86 | 2 | Nature Conservancy | Fort Jackson Woods (Action Site_N.C.) | Plaquemines | |
| 87 | 2 | Nature Conservancy | Lake Boeuf (Action Site_N.C.) | Lafourche | |
| 88 | 1 | Nature Conservancy | Lake Pontchartrain Wetlands (Action Site_N.C.) | Multiple | |
| 89 | 2 | Nature Conservancy | Grand Isle/Barataria Bay Complex (Portfolio Site_N.C.) | Lafourche/Jefferson/Plaquemines | |
| 90 | 2 | Nature Conservancy | River Aux Chenes Forest (Portfolio Site_N.C.) | Plaquemines | |
| 91 | 2 | Nature Conservancy | Abandoned Channel of Bayou Barataria (Portfolio Site_N.C.) | Jefferson | |
| 92 | 3 | Nature Conservancy | Central LA Barrier Islands and Beaches | Terrebonne/Lafourche | |
| 93 | 2 | Nature Conservancy | Jean Lafitte NP (Portfolio Site_N.C.) | Jefferson | |
| 94 | 2 | Nature Conservancy | Caernarvon Marshes (Portfolio Site_N.C.) | Plaquemines | |
| 95 | 2 | Nature Conservancy | Des Allemands Marsh (Portfolio Site_N.C.) | St. John/Lafourche/St. Charles | |
| 96 | 2 | Nature Conservancy | Delta Farms Marshes (Portfolio Site_N.C.) | Lafourche | |
| 97 | 1 | Nature Conservancy | Chandeleur Sound (Portfolio Site_N.C.) | St. Bernard/Plaquemines | |
| 98 | 2 | Nature Conservancy | Lake Salvador (Portfolio Site_N.C.) | St. Charles/Jefferson/Lafourche | |
| 99 | 1 | CIAP/Livingston Parish | Hydrologic Restoration in the Swamps West of Lake Maurepas/Spoil Bank Gapping Amite River Diversion Canal | Livingston | |
| 101 | 1 | CWPPRA | Shoreline Protection and Marsh Creation Along Lake Borgne and MRGO | St. Bernard | |
| 103 | 2 | CWPPRA | Shell Island Barrier Headland Restoration | Plaquemines | |
| 104 | 2 | CWPPRA | East Fourchon Marsh Creation and Terracing | Lafourche | |
| 105 | 3 | CWPPRA | North Bully Camp Hydrologic Restoration/Marsh Creation | Lafourche | |
| 109 | 4 | CWPPRA | Gulf of Mexico Shoreline Stabilization Joseph's Harbor east | Cameron/Vermilion | |
| 113 | 1 | St. Bernard Parish (SBE) | Wetland Creation at Nunez College | St. Bernard | $300000.00 |
| 114 | 1 | St. Bernard Parish (SBE) | Wetland Creation along Paris Rd. | St. Bernard | $200000.00 |
| 116 | 2 | Ducks Unlimited (DU) | Pass -a-Loutre WMA Crevasse Splays | Plaquemines | $100000.00 |
| 117 | 4 | Ducks Unlimited (DU) | LA Coastal Wetlands II Terraces Jim Bell | Cameron | |
| 118 | 4 | Ducks Unlimited (DU) | LA Coastal Wetlands II Terraces Miami Corporation | Cameron | |
| 119 | 4 | Ducks Unlimited (DU) | LA Coastal Wetlands II Terraces Vermilion Corporation | Vermilion | |
| 120 | 4 | Ducks Unlimited (DU) | Sterling Oaks Hydrologic Restoration | Cameron | $150000.00 |
| 121 | 3 | Ducks Unlimited (DU) | Pointe au Chien Hydrological Restoration | Terrebonne | $1000000.00 |
| 122 | 4 | Ducks Unlimited (DU) | Pecan Island Hydrologic Restoration | Vermilion | $250000.00 |
| 123 | 3 | Ducks Unlimited (DU) | Avoca Island Hydrologic Restoration | St. Mary | $550000.00 |
| 124 | 4 | Ducks Unlimited (DU) | Cheniere Plain Coastal Wetlands Restoration | Cameron | $999800.00 |
| 125 | 2 | Jefferson Parish Dept of Environmental Affairs | Grand Pierre Island Restoration (BS-1) | Plaquemines | |
| 126 | 2 | Jefferson Parish Dept of Environmental Affairs | Elmer's Island and West Grande Terre Oak Ridge Restoration (BI-4) | Lafourche/Jefferson | |
| 127 | 2 | Jefferson Parish Dept of Environmental Affairs | Caminada Chenier Restoration (FN-1) | Lafourche | |
| 128 | 2 | Jefferson Parish Dept of Environmental Affairs | Grand Isle Plan (BI-6) | Jefferson | |
| 129 | 2 | CWPPRA/Jefferson Parish Dept of Environmental Affairs | Naomi Siphon Sediment Enrichment (NA-1) | Plaquemines | |
| 130 | 2 | Jefferson Parish Dept of Environmental Affairs | Hero Canal Diversion (NA-7) | Plaquemines | |
| 131 | 2 | Jefferson Parish Dept of Environmental Affairs | Bayou Dupont Sediment Delivery Expansion (NA-9) | Plaquemines/Jefferson | |
| 133 | 2 | Jefferson Parish Dept of Environmental Affairs | Myrtle Grove Natural Ridge Restoration (MG-1) | Jefferson | |
| 134 | 2 | Jefferson Parish Dept of Environmental Affairs | Bayou Segnette Shoreline Restoration at Yankee Pond (CS-5) | Jefferson | |
| 135 | 2 | Jefferson Parish Dept of Environmental Affairs | North of Yankee Pond Restoration (CS-6) | Jefferson | |
| 136 | 2 | Jefferson Parish Dept of Environmental Affairs | Southeast Lake Salvador near Bayou Villars Shoreline Protection/Stabilization (CS-9) | Jefferson | |
| 137 | 2 | Jefferson Parish Dept of Environmental Affairs | Northeast Lake Salvador Chenier Restoration (CS-10) | Jefferson | |
| 138 | 2 | Jefferson Parish Dept of Environmental Affairs | North Cuba Island Shoreline Protection | St. Charles | |
| 139 | 2 | Jefferson Parish Dept of Environmental Affairs | Tenneco Canal Restoration-National Park Service (CS-18) | Jefferson | |
| 140 | 2 | Jefferson Parish Dept of Environmental Affairs | Goose Bayou to Cypress Bayou Shoreline Protection (NA-3) | Jefferson | |
| 141 | 2 | Jefferson Parish Dept of Environmental Affairs | South Shore of the Pen Shoreline Protection/Stabilization (MG-5) | Jefferson | |
| 142 | 2 | Jefferson Parish Dept of Environmental Affairs | Land Bridge Shoreline Protection Extension and Wetland Protection (PR-7) | Jefferson | |
| 143 | 2 | Jefferson Parish Dept of Environmental Affairs | Bayou Perot/Bayou Rigolettes Peninsula Restoration (PR-11) | Jefferson | |
| 144 | 2 | Jefferson Parish Dept of Environmental Affairs | Bay Dosgris Vicinity Wetlands Restoration | Jefferson | |
| 145 | 2 | Jefferson Parish Dept of Environmental Affairs | Mud Lake Vicinity Wetland Restoration (LL-5) | Jefferson | |
| 146 | 2 | Jefferson Parish Dept of Environmental Affairs | BBWW from Bayou Normand to Bayou St. Denis Shoreline Restoration (LL-6) | Jefferson | |
| 147 | 2 | Jefferson Parish Dept of Environmental Affairs | North Barataria Bay Shoreline Wave Breaks | Jefferson | |
| 148 | 2 | Jefferson Parish Dept of Environmental Affairs | Whiskey Canal Wetland Enhancement (CS-19) | Jefferson | |
| 149 | 2 | Jefferson Parish Dept of Environmental Affairs | Dupre Cut Project 9 (BA-26) Wetlands Restoration (MG-3) | Jefferson | |
| 150 | 2 | Jefferson Parish Dept of Environmental Affairs | Lafitte Oil and Gas Field (East) Restoration (MG-2) | Jefferson | |
| 151 | 2 | Jefferson Parish Dept of Environmental Affairs | Manila Oil and Gas Restoration (MG-4) | Jefferson | |
| 152 | 2 | Jefferson Parish Dept of Environmental Affairs | Little Lake Hunting Club Wetland Restoration (PR-3) | Jefferson | |
| 153 | 2 | JEF | Delta Farms Oil and Gas Field Restoration (PR-6) | Lafourche | |
| 154 | 2 | JEF | Bayou Rigolettes Bayou Perot and Harvey Cut Channel Management (PR-1) | Jefferson, Lafourche | |
| 155 | 2 | Jefferson Parish Dept of Environmental Affairs | Dupre Cut/Barataria Bay Waterway Channel Management (PR-2) | Jefferson | |
| 156 | 2 | Jefferson Parish Dept of Environmental Affairs | Bayou St. Denis Channel Management (LL-1) | Jefferson | |
| 158 | 2 | Jefferson Parish Dept of Environmental Affairs | Wetland Harbor Activities Recreational Facility (WHARF) (CS-4) | Jefferson | |
| 159 | 2 | Jefferson Parish Dept of Environmental Affairs | Elmer's Island Acquisition and Preservation (BI-3) | Jefferson | |
| 160 | 1 | Jefferson Parish Dept of Environmental Affairs | La Branche Wetlands Drainage Diversion (JE-1) | Jefferson | |
| 161 | 1 | Jefferson Parish Dept of Environmental Affairs | Lake Pontchartrain Drainage treatment (JE-2) | Jefferson | |
| 162 | 2 | Jefferson Parish Dept of Environmental Affairs | North Bayou Segnette Water Quality Improvement Project (CS-1) | Jefferson | |
| 163 | 2 | Jefferson Parish Dept of Environmental Affairs | Bayou Segnette Wetlands Sewage Effluent Diversion (CS-3) | Jefferson | |
| 164 | 2 | Jefferson Parish Dept of Environmental Affairs | Rosethorne Wetlands Sewage Effluent Diversion (NA-6) | Jefferson | |
| 166 | 2 | JEF | Barataria Basin Barrier Levee (BW-1) | Jefferson, Lafourche, Plaquemines | |
| 169 | 2 | Jefferson Parish Dept of Environmental Affairs | Jones Point Shipyard Wetland Restoration-National Park Service (CS-17) | Jefferson | |
| 171 | 2 | Jefferson Parish Dept of Environmental Affairs | Grand Isle Oil and Gas Pipeline Corridor Shoreline Protection (BI-5) | Jefferson | |
| 172 | 2 | Lafourche Basin Levee District | South of Clovelly Farms Levee Stabilization (C1) | Lafourche | $6778000.00 |
| 173 | 2 | Lafourche Basin Levee District | East of Clovelly Farms Levee Stabilization (C2) | Lafourche | $2500000.00 |
| 174 | 2 | Lafourche Basin Levee District | North of Clovelly Farms Levee Stabilization (C2) | Lafourche | $1961000.00 |
| 175 | 2 | Lafourche Basin Levee District | Delta Farms Levee Stabilization (C4) | Lafourche | $4480000.00 |
| 176 | 2 | Lafourche Basin Levee District | GIWW Bank Stabilization Phase 1 (C5) | Lafourche | $6400000.00 |
| 177 | 2 | Lafourche Basin Levee District | GIWW Bank Stabilization Phase 2 (C6) | Lafourche | $9600000.00 |
| 178 | 2 | Lafourche Basin Levee District | GIWW Bank Stabilization Phase 3 (C7) | Lafourche | $9590000.00 |
| 179 | 2 | Lafourche Basin Levee District | Bayou Perot Shoreline Protection (C8) | Lafourche | $4290400.00 |
| 180 | 2 | Lafourche Basin Levee District | West of Bayou Perot Marsh Creation (C9) | Lafourche | $3647300.00 |
| 181 | 2 | Lafourche Basin Levee District | North of Little Lake Phase 1 Marsh Creation (C10) | Lafourche | $8905600.00 |
| 182 | 2 | Lafourche Basin Levee District | North of Little Lake Phase 2 Marsh Creation (C11) | Lafourche | $2283600.00 |
| 183 | 2 | Lafourche Basin Levee District | South of Yankee Canal Freshwater Diversion (LE1) | Lafourche | $700000.00 |
| 184 | 2 | Lafourche Basin Levee District | Pointe Fourchon LA Highway 1 Ridge Protection (CB1) | Lafourche | $3140300.00 |
| 185 | 2 | Lafourche Basin Levee District | Lake Laurier LA Highway 1 Ridge Protection (CB2) | Lafourche | $1433600.00 |
| 186 | 2 | Lafourche Basin Levee District | Bay Jacques Hydrologic Restoration (CB3) | Lafourche | $8103000.00 |
| 187 | 2 | Lafourche Basin Levee District | Tidewater Canal Hydrologic Restoration (CB4) | Lafourche | $8154600.00 |
| 188 | 2 | Lafourche Basin Levee District | Golden Meadow Farms Hydrologic Restoration (CB5) | Lafourche | $9270200.00 |
| 189 | 2 | Lafourche Basin Levee District | Hydrologic Restoration South of Bayou L'ours Ridge (LL1) | Lafourche | $8700700.00 |
| 190 | 2 | Lafourche Basin Levee District | Marsh Rim Establishment on the South Shore of Little Lake (LBLD1) | Lafourche | $9742500.00 |
| 191 | 2 | Lafourche Basin Levee District | East Snail Bay Shoreline Protection (LBLD2) | Lafourche | $3791700.00 |
| 192 | 2 | Lafourche Basin Levee District | West of Snail Bay Shoreline Protection and Marsh Creation (LBLD3) | Lafourche | $10981700.00 |
| 193 | 2 | Lafourche Basin Levee District | Live Oak Bay Shoreline Protection (LBLD4) | Lafourche | $7960000.00 |
| 194 | 2 | Lafourche Basin Levee District | Hackberry Bay North Island Restoration (LBLD5) | Lafourche | $7407000.00 |
| 195 | 2 | Lafourche Basin Levee District | West Champagne Bay Marsh Creation (LBLD6) | Lafourche | |
| 196 | 2 | Lafourche Basin Levee District | Caminada Bay Breakwaters (LBLD7) | Lafourche | $12936300.00 |
| 197 | 2 | Lafourche Basin Levee District | Lake Palourde Tidal Restriction (LBLD8) | Lafourche | $5000000.00 |
| 198 | 2 | Lafourche Basin Levee District | Caminada Bay Marsh Creation (LBLD9) | Lafourche | $16603000.00 |
| 202 | 1 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Lake Borgne/MS Sound | St. Bernard | |
| 203 | 1 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Primary Seed Grounds | St. Bernard/Plaquemines | |
| 204 | 2 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Hackberry Bay | Jefferson/Lafourche | |
| 205 | 2 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Barataria Bay | Jefferson | |
| 206 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Deep Lake | Lafourche | |
| 207 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Lake Felicity | Terrebonne | |
| 208 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Lake Chien | Terrebonne | |
| 209 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Lake Tambour | Terrebonne | |
| 210 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Lake Mechant | Terrebonne | |
| 211 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Sister (Caillou) Lake | Terrebonne | |
| 212 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Bay Junop | Terrebonne | |
| 213 | 3 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Vermilion/Atchafalaya Bays | St. Mary/Iberia/Vermilion | |
| 214 | 4 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Calcasieu Lake | Cameron | |
| 215 | 4 | LDWF/Marine Fisheries Division | Cultch Placement for Oyster Enhancement - Sabine Lake | Cameron | |
| 216 | 2 | CWPPRA | Caernarvon Diversion Outfall Management (East) BS-5-2 | St. Bernard/Plaquemines | |
| 217 | 4 | CWPPRA | Oyster Bayou Terracing | Cameron | |
| 219 | 3 | CWPPRA | Shark Island Shoreline Protection | Iberia | $18160000.00 |
| 221 | 3 | Morris P. Hebert/LDWF | LDWF Marsh Creation (Pointe-au-Chien WMA) | Lafourche | |
| 222 | 3 | Morris P. Hebert/Burlington Resources | Grand Bayou Blue dredge and Fill | Lafourche | |
| 223 | 3 | Morris P. Hebert | Fanguy Marsh Creation Project | Terrebonne | |
| 225 | 2 | Morris P. Hebert/Edward Wisner | Edward Wisner Marsh Creation | Lafourche | |
| 226 | 2 | St. James Parish | Hydrologic Restoration / South Vacherie | St. James | |
| 227 | 1 | St. James Parish | Levee Gapping / East Bank St. James Parish | St. James | |
| 228 | 2 | St. James Parish | Levee Gapping / West Bank St. James Parish | St. James | |
| 229 | 1 | St. James Parish | Wetland Creation-Parishwide / East Bank | St. James | |
| 230 | 1 | St. James Parish | Grand Point Boat Launch | St. James | |
| 231 | 2 | CIAP | Lake Lery Shoreline Protection | St. Bernard | |
| 232 | 2 | CWPPRA | Shell Island Barrier Protection (2-4) | Plaquemines | |
| 233 | 2 | St. James Parish | Wetland Creation-Parishwide / West Bank | St. James | |
| 234 | 3 | Vermilion Parish Coastal Restoration Advisory Committee | Bird Island Habitat | Vermilion | |
| 235 | 3 | Vermilion Parish Coastal Restoration Advisory Committee | Little Vermilion Bay-Lagoons/Rookery | Vermilion | |
| 236 | 3 | Vermilion Parish Coastal Restoration Advisory Committee | Four Mile Canal/Bar Mouth | Vermilion | |
| 238 | 3 | Assumption Parish Police Jury/OEP | Bayou Bonier | Assumption | |
| 239 | 3 | CIAP/Assumption Parish | Lake Verret Shoreline | Assumption | |
| 240 | 3 | Assumption Parish Police Jury/OEP | Cancienne Canal | Assumption | |
| 241 | 3 | Assumption Parish Police Jury/OEP | Bayou Corne and Grand Bayou | Assumption | |
| 242 | 3 | Assumption Parish Police Jury/OEP | Himalaya/Lower Texas Canal | Assumption | |
| 244 | 3 | Crooked Bayou Hunting Club | Plumb Island Point Terracing/Hydrologic Restoration | St. Mary | |
| 245 | 2 | Morris P. Hebert/Edward Wisner | Bay Champagne Marsh Creation/North Rim | Lafourche | |
| 246 | 2 | Morris P. Hebert/Wayne Martin | Martin Shoreline Protection and Marsh Creation | Lafourche | |
| 247 | 3 | Nature Conservancy | Bayou Mauvais Bois Ridge | Terrebonne | |
| 248 | 3 | Nature Conservancy | Cote Blanche Salt Dome | St. Mary | |
| 249 | 3 | Nature Conservancy | Weeks Island | Iberia | |
| 250 | 3 | Nature Conservancy | Avery Island | Iberia | |
| 252 | 3 | Nature Conservancy | Palmetto Island | Vermilion | |
| 254 | 3 | CWPPRA | Havoline Canal Dedicated Dredging Back Barrier Marsh Creation | Terrebonne/Lafourche | |
| 255 | 3 | CWPPRA | Hydrologic Restoration of Plumb Island Point to Palmetto Bayou | Terrebonne | |
| 257 | 1 | CWPPRA | Bank Stabilization Lake Borgne - Bayou Dupre to Bayou Bienvenue (1-1) | St. Bernard | |
| 259 | 4 | CWPPRA | Shoreline Stabilization for Freshwater Bayou Canal (4-2) | Vermilion | |
| 260 | 4 | CWPPRA | Black Bayou Hydrologic Restoration, Phase II (4-4) | Calcasieu/Cameron | |
| 261 | 1 | Woodlands Conservancy | Woodlands Trail - Phase One | Plaquemines | |
| 262 | 2 | Woodlands Conservancy | Woodlands Trail - Greenway Corridor Project | Orleans/Plaquemines | |
| 263 | 2 | Woodlands Conservancy | Sugar Mill and Plantation Project | Orleans | |
| 264 | 2 | Woodlands Conservancy | Woodlands Trail - Interpretive Center | Plaquemines | |
| 266 | 3 | Mandalay National Wildlife Refuge - USFWS | Mandalay National Wildlife Refuge (NWR) | Terrebonne | |
| 267 | 3 | C-K Associates, LLC | CFW Conversion Project near Pointe au Chien WMA | Terrebonne | |
| 268 | 3 | C-K Associates, LLC | Bayou la Cache CFW Conversion near Chauvin | Terrebonne | |
| 269 | 3 | C-K Associates, LLC | Bayou Grand Coteau CFW Conversion Project | Terrebonne | |
| 271 | 2 | LDWF/Pass-a-Loutre WMA | Pass-a-Loutre WMA Barrier Islands (Beneficial Use) | Plaquemines | $30000000.00 |
| 272 | 2 | USFWS/Breton-Delta NWR | Delta-Breton NWR Main Pass Crevasse Splay | Plaquemines | |
| 273 | 2 | USFWS/Breton-Delta NWR | Delta-Breton NWR South Bank of Octave Pass Crevasse Splay | Plaquemines | |
| 274 | 2 | LDWF/Pass-a-Loutre WMA | Pass-a-Loutre Dredge and Fill Marsh Creation | Plaquemines | $90000000.00 |
| 275 | 2, 3 | LDWF/Pinte aux Chenes WMA | Bayou Pointe Aux Chenes Fishing Piers | Lafourche, Terrebonne | |
| 276 | 3 | LDWF | Grand Bayou Water Management Unit #2 | Lafourche | |
| 277 | 2 | LDWF | Pass-a-Loutre & Atchafalaya Delta WMA Campground Improvements | Plaquemines | |
| 278 | 2 | LDWF | Sawdust Bend Marsh Creation | Plaquemines | |
| 279 | 3 | LDWF | Grand Bayou Water Management Unit #4 | Lafourche | |
| 280 | 3 | Conestoga-Rovers and Associates | Canal Filling Along Southeast Mosquito Bay (Site 1) | Terrebonne | |
| 281 | 3 | Conestoga-Rovers and Associates | Canal Filling Along East Mosquito Bay (Site 2) | Terrebonne | |
| 282 | 3 | Conestoga-Rovers and Associates | Canal Filling Southwest of Mosquito Island (Site 3) | Terrebonne | |
| 283 | 3 | Conestoga-Rovers and Associates | Shoreline Protection North of the Inlet to Mosquito Bay (Site 4) | Terrebonne | |
| 284 | 1 | CWPPRA | Bayou Bienvenue Marsh Creation and Freshwater Diversion | Orleans/St. Bernard | $59000000.00 |
| 285 | 1 | CWPPRA | Lake Athanasio Shoreline Protection and Dedicated Marsh Creation | St. Bernard | $15000000.00 |
| 286 | 1 | CWPPRA | Mississippi River Redistribution at Violet | St. Bernard | $30000000.00 |
| 287 | 1 | CWPPRA | Rigolettes Shoreline Protection | Orleans | $3000000.00 |
| 288 | 2 | CWPPRA | Cheniere Caminada Barrier Headland Restoration | Lafourche | $10700000.00 |
| 289 | 2 | CWPPRA | Mississippi River Small Redistribution (Siphon) and Outfall Management East of Lac des Allemands | St. Charles | $12000000.00 |
| 290 | 2 | CIAP | Northwest Little Lake Marsh Creation and Enhancement | Lafourche | |
| 291 | 2 | CWPPRA | Pass-a-Loutre Sediment Mining | Plaquemines | $33000000.00 |
| 292 | 4 | Bel Commercial | Bel Commercial Tallow Tree Reclamation Area | Calcasieu | |
| 293 | 4 | Gardner Garrison | Old Settlement Terrace Mitigation Area | Cameron | |
| 294 | 4 | Bel Krause Properties | Goose Lake Prairie Restoration | Calcasieu | |
| 295 | 4 | Bel Krause Properties | Goose Lake GIWW Armoring | Calcasieu | |
| 296 | 4 | Pine Pasture, LLC | Shell Ditch Restoration | Cameron | |
| 298 | 2 | Jefferson Parish | Fifi Island Marsh Restoration | Jefferson | |
| 299 | 2 | Jefferson Parish | NE Little Lake Shore Protection and Marsh Creation | Jefferson | $14000000.00 |
| 300 | 1 | USDA/NRCS - Green Fund | West End Cypress Swamp Project - Mandeville, LA | St. Tammany | $1200000.00 |
| 301 | 3 | Defenders of Wildlife/National Wildlife Refuge Association | Bayou Teche NWR Land Acquisition - Bailey Parcel | St. Mary | $5000000.00 |
| 302 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Bayou Sauvage NWR Land Acquisition - Big Oak Island Parcel | Orleans | $1500000.00 |
| 303 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Bayou Sauvage NWR Land Acquisition - Cummings Parcel | Orleans | $400000.00 |
| 304 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Bayou Sauvage NWR Land Acquisition - Audubon Parcel | Orleans | $150000.00 |
| 305 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Jones Parcel | St. Tammany | $1550000.00 |
| 306 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Mentab Parcel | St. Tammany | $1200000.00 |
| 307 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - McCrae Parcel | St. Tammany | $360000.00 |
| 308 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Benjamin/Dunbar Parcel | St. Tammany | $640000.00 |
| 309 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Lindsey Parcel | St. Tammany | $200000.00 |
| 310 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Log Bayou Parcel | St. Tammany | $72000.00 |
| 311 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Bopp Parcel | St. Tammany | $162000.00 |
| 312 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Blossman Parcel | St. Tammany | $260000.00 |
| 313 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Big Branch Marsh NWR Land Acquisition - Wood Parcel | St. Tammany | $108000.00 |
| 318 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Bayou Sauvage NWR Land Acquisition - Brazalier Carter Parcel | Orleans | $40000.00 |
| 319 | 1 | Defenders of Wildlife/National Wildlife Refuge Association | Bayou Sauvage NWR Land Acquisition - Powers Junction Parcel | Orleans | $150000.00 |
| 320 | 2 | Grey K Environmental | Clovelly | Lafourche | |
| 321 | | Living Waters International | Aquaculture Building Communities-restocking the Gulf and LA marshlands | Coastwide | |
| 322 | 2 | BTNEP | Restoring Small Islands in Barataria Bay: Providing Habitat for Nesting Birds | Plaquemines | $2647540 |
| 323 | 2 | BTNEP | Habitat Restoration for Nesting Birds in Barataria Bay (Multiple Islands) | Plaquemines | $10590160.00 |
| 324 | 3 | LDNR | 16" and 21" Pipeline Canals | St. Martin | $256261.00 |
| 326 | 3 | Terrebonne Parish | Atchafalaya Long Distance Sediment Pipeline | Terrebonne | $570000000.00 |
| 327 | 3 | CWPPRA | Avoca Island Diversion and Land Building | St. Mary | $19200000.00 |
| 328 | 2 | Plaquemines Parish | Baptiste Collette Jetty Extension | Plaquemines | |
| 329 | 3 | LCA | Barataria Basin Barrier Shoreline Restoration - Caminada Headland | Lafourche | $420000000.00 |
| 330 | 2 | CIAP/Jefferson Parish | Bay Dosgris Vicinity Wetland Restoration | Jefferson | $28480000.00 |
| 331 | 2 | Jefferson Parish | Bay Side Segmented Breakwater at Grand Isle | Jefferson | $10000000.00 |
| 332 | 2 | CWPPRA | Bayou Dupont Marsh and Ridge Creation Project | Jefferson | $43000000.00 |
| 333 | 2 | CWPPRA Candidate/Parish | Bayou Dupont to Bayou Barataria Marsh Creation | Jefferson | $20000000.00 |
| 334 | 2 | Jefferson Parish | Bayou Rigolettes, Bayou Perot, and Harvey Cut Channel Management | Jefferson | $2770000.00 |
| 335 | 3 | CWPPPA | Bayou Sale Shoreline Protection | St. Mary | $40600000.00 |
| 336 | 3 | LCA | Bayou Terrebonne Bank Stabilization/Bush Canal/Seabreeze Embankment | Terrebonne | $7000000.00 |
| 337 | 3 | LDWF | Bayou Terrebonne Freshwater Diversion | Terrebonne | $6000000.00 |
| 338 | 2 | CWPPRA | Bayou Villars Shoreline Stabilization | Jefferson | $10000000.00 |
| 339 | 2 | CWPPRA | Bertrandville Siphon | Plaquemines | $22500000.00 |
| 340 | 3 | LDNR | Big Bayou Pigeon | Iberia | $484296.00 |
| 341 | 1 | State | Biloxi Marsh Shoreline Protection Phase 2 | St. Bernard | $44376689.00 |
| 342 | 2 | CWPPRA | Bohemia Mississippi River Reintroduction Project | Plaquemines | $6900000.00 |
| 343 | 2 | Jefferson Parish | Breakwaters on Grand Isle | Jefferson | $40000000.00 |
| 344 | 3 | LDWF | Bully Camp Marsh and Grand Bayou Marsh Terracing | Lafourche | $2500000.00 |
| 345 | 3 | LDWF | Bully Camp Marsh Management | Lafourche | $4750000.00 |
| 346 | 2 | CWPPRA | Caernarvon Outfall Management/Lake Lery Shoreline Protection Project | Plaquemines | $30000000.00 |
| 347 | 4 | | Cameron Shoreline | Cameron | $45800000.00 |
| 348 | 4 | CWPPRA | Cameron-Creole Freshwater Introduction | Cameron | $12700000.00 |
| 349 | 2 | Plaquemines Parish | Cat Island Restoration | Plaquemines | $5000000.00 |
| 350 | 3 | CWPPRA | Central Terrebonne Freshwater Enhancement | Terrebonne | $16600000.00 |
| 351 | 1 | State/DOI | Chandeleur Islands Restoration | St. Bernard | $65000000.00 |
| 352 | 2 | CWPPRA | Cheniere Ronquille Barrier Island Restoration | Plaquemines | $40000000.00 |
| 353 | 3 | LCA | Convey Atchafalaya River to Northern Terrebonne Marshes/Construction and Multi-purpose Operation of Houma Navigation Lock | Lafourche/Terrebonne/St. Mary | $305500000.00 |
| 354 | 2 | Jefferson Parish | Dupre Cut/Barataria Bay Waterway Channel Management | Jefferson | $7600000.00 |
| 355 | 2 | Plaquemines Parish | Empire Waterway Dredging, Bank Stabilization and Rocking | Plaquemines | |
| 356 | 2 | CIAP/Jefferson Parish | Fifi Island Restoration Extension | Jefferson | $12500000.00 |
| 357 | 2 | Plaquemines Parish | Forested Ridge - Boothville to Venice | Plaquemines | $45000000.00 |
| 358 | 2 | Plaquemines Parish | Forested Ridge - Braithewaite to Bohemia | Plaquemines | $90000000.00 |
| 359 | 2 | Plaquemines Parish | Forested Ridge - Empire to Boothville | Plaquemines | $73125000.00 |
| 360 | 2 | Plaquemines Parish | Forested Ridge - Pointe a la Hache | Plaquemines | $101250000.00 |
| 361 | 2 | Plaquemines Parish | Forested Ridge - Port Sulphur to Empire | Plaquemines | $84375000.00 |
| 362 | 1 | SLFPA-E | Frenier Wetlands/Bonnet Carre River re-introduction | St. John/St. Charles | |
| 363 | 3 | CWPPRA | Freshwater Bayou Bank Stabilization - Belle Isle Canal to Lock | Vermilion | $38000000.00 |
| 364 | 4 | CWPPRA | Freshwater Bayou Marsh Creation (CWPPRA) | Vermilion | $25500000.00 |
| 365 | 2 | LDWF | Grand Bayou #2 Marsh Management and Enhancement | Lafourche | $2200000.00 |
| 366 | 4 | CIAP/State | Grand Lake Shoreline Protection, Tebo Point | Cameron | $13600000.00 |
| 367 | 2 | CWPPRA | Grand Liard Marsh and Ridge Restoration | Plaquemines | $30000000.00 |
| 368 | 2 | Plaquemines Parish | Grand Pass Bank Armoring | Plaquemines | |
| 369 | 2 | Jefferson Parish | Grand Terre Hatchery | Jefferson | $22000000.00 |
| 370 | 3 | LCA | Gulf Shoreline at Point au Fer Island | Terrebonne | $43400000.00 |
| 373 | 1 | CIAP | La Branche East Marsh Creation | St. Charles | $32300000.00 |
| 374 | 2 | Jefferson Parish | Lafitte Oilfield (West) Canal Closures | Jefferson | $5000000.00 |
| 375 | 3 | CWPPRA Nominee/Parish | Lake Barre Marsh Creation | Terrebonne | $25900000.00 |
| 376 | 2 | CWPPRA | Lake Hermitage Additional Increment (Lake Hermitage Marsh Creation – NRDA Early Restoration Project) | Plaquemines | $13963956 |
| 377 | 1 | CIAP/Tangipahoa Parish | Lake Pontchartrain shoreline restoration | St. John/Tangipahoa | |
| 378 | 2 | Terrebonne Parish | Lake Tambour Marsh Creation | Terrebonne | $17500000.00 |
| 379 | 3 | LDNR | Little Bayou Pigeon | Iberia/St. Marten | $522750.00 |
| 380 | 2 | CIAP/State | Long Distance Sediment Pipeline - Phase 1 and 2 | Plaquemines/Jefferson | $388000000.00 |
| 381 | 3 | CWPPRA | Lost Lake Marsh Creation and Hydrologic Restoration | Terrebonne | $22900000.00 |
| 382 | 3 | CWPPRA | Madison Bay Marsh Creation and Terracing | Terrebonne | $35000000.00 |
| 383 | 3 | LCA | Maintain Land bridge between Caillou Lake and Gulf of Mexico | Terrebonne | $56300000.00 |
| 384 | 2 | Jefferson Parish | Manila Oil and Gas Field Restoration | Jefferson | $2070000.00 |
| 385 | 2 | LCA | Medium Diversion at White Ditch | Plaquemines | $387620000.00 |
| 386 | 2 | LCA | Medium Diversion with Dedicating Dredging at Myrtle Grove | Jefferson | $278300000.00 |
| 387 | 2 | CWPPRA | Mississippi River Reintroduction Into Northwest Barataria Basin | St. John/St. James/Lafourche | $17100000.00 |
| 388 | 2 | LCA | Modification of Caernarvon Diversion | Plaquemines | $20700000.00 |
| 389 | 2 | LCA | Modification of Davis Pond Diversion | St. Charles | $64200000.00 |
| 390 | 1 | WRDA07 | MRGO Environmental Restoration including Violet Diversion | St. Bernard/Orleans | $3000000000.00 |
| 391 | 2 | Jefferson Parish | Mud Lake Vicinity Wetland Restoration | Jefferson | $8420000.00 |
| 392 | 2 | LCA | Myrtle Grove - Marsh Platform | Jefferson | |
| 393 | 2 | Plaquemines Parish | Naomi Siphon Outflow Maintenance Dredging | Plaquemines | |
| 394 | 2 | Jefferson Parish | North Barataria Wavebreak | Jefferson | $42600000.00 |
| 395 | 3 | CWPPRA | North Lake Boudreaux Basin Freshwater Introduction and Hydrologic Management | Terrebonne | $25800000.00 |
| 396 | 2 | CWPPRA Nominee/Parish | Northeast Little Lake Shoreline Protection and Marsh Creation | Jefferson | $14000000.00 |
| 397 | 3 | LDNR | Open Brown Bayou to the I-10 Canal | Iberville | $308731.00 |
| 398 | | LDNR | Orphan Well Projects | Coastwide | $31300000.00 |
| 399 | CW | LDWF | Oyster Reestablishment Program (Louisiana Oyster Cultch Project) | Gulfwide | $15000000 |
| 400 | 2 | LDWF | Pass-a-Loutre Crevasse Clean-out | Plaquemines | $108500000.00 |
| 401 | 2 | LDWF | Pass-a-Loutre Restoration | Plaquemines | $98000000.00 |
| 402 | 2 | LDWF | Pass-a- Loutre WMA Marsh Creation | Plaquemines | $1200000.00 |
| 403 | 2 | Plaquemines Parish | Port Eads Marina | Plaquemines | |
| 404 | 3 | LDWF | Raccoon Island Restoration and Protection | Terrebonne | $30000000.00 |
| 405 | 1 | CWPPRA | River Reintroduction into Maurepas Swamp | St. John/St.James | $164000000.00 |
| 406 | 4 | CWPPRA | Rockefeller Refuge Gulf Shoreline Stabilization | Cameron | $160000000.00 |
| 407 | | LDWF | Saltwater Hatchery | Gulf Wide | $48500000.00 |
| 408 | 2 | LDWF | Sediment Mining at Pass-a-Loutre | Plaquemines | $123500000.00 |
| 409 | 2 | CPRA | Shell Island - Larger Lobe | Plaquemines | $110773509.00 |
| 410 | 3 | CWPPRA/Candidate/Parish | Ship Shoal: Whiskey West Flank Restoration | Terrebonne | $61800000.00 |
| 411 | 2 | LCA | Small Bayou Lafourche Reintroduction | Lafourche/Ascension | $175000000.00 |
| 412 | 1 | LCA | Small Diversion at Convent / Blind River | ST. JAMES | $123140000.00 |
| 413 | 1 | LCA | Small Diversion at Hope Canal | St. John | $150000000.00 |
| 414 | 3 | CWPPRA | Southwest Louisiana Gulf Shoreline Nourishment and Protection | Iberia | $36900000.00 |
| 415 | 2 | CWPPRA | Spanish Pass Diversion | Plaquemines | $14200000.00 |
| 416 | 3 | LCA | Terrebonne Basin Barrier Shoreline Restoration / Including Ship Shoal: Whiskey West Flank | Lafourche/Terrebonne | $689000000.00 |
| 417 | 3 | Terrebonne Parish | Terrebonne Bay Landbridge | Terrebonne/Lafourche | $175000000.00 |
| 418 | 3 | CWPPRA Candidate/Parish | Terrebonne Bay Marsh Creation and Nourishment | Terrebonne | $25100000.00 |
| 419 | 2 | Plaquemines Parish | Tiger Pass Jetty Extension | Plaquemines | |
| 420 | 2 | Plaquemines Parish | Tiger Pass Marsh and Ridge Restoration | Plaquemines | $13750000.00 |
| 421 | 2 | LDWF | Timken Shoreline Protection | St. Charles | $5500000.00 |
| 422 | 2 | CWPPRA | Venice Ponds Marsh Creation and Crevasses | Plaquemines | $9000000.00 |
| 423 | 3 | CWPPRA | Weeks Bay Marsh Creation and Shore Protection/Commercial Canal Freshwater Redirection | Iberia | $30000000.00 |
| 424 | 2 | Jefferson Parish | West Grand Terre Beach | Jefferson | $9000000.00 |
| 425 | 2 | Jefferson Parish | West Grand Terre Stabilization | Jefferson | $3000000.00 |
| 426 | 2 | CWPPRA | West Pointe a la Hache Marsh Creation Project | Plaquemines | $16100000.00 |
| 427 | 2 | CWPPRA | West Pointe a la Hache Outfall Management | Plaquemines | $5400000.00 |
| 428 | 2 | Plaquemines Parish | West Pointe a la Hache Siphon outflow maintenance dredging | Plaquemines | |
| 429 | 3 | LDWF | Whiskey Island Protection | Terrebonne | $30000000.00 |
| 430 | 2 | LCA | White's Ditch Marsh Platform | Plaquemines | |
| 431 | 3 | LDWF | Wine Island Restoration/Protection | Terrebonne | $30000000.00 |
| 432 | 2 | LDWF | Mangrove Island Extension | Plaquemines | $30000000.00 |
| 433 | 2 | LDWF | Queen Bess Island East | Lafourche | $30000000.00 |
| 434 | 3 | Nature Conservancy | TNC Oyster Reef in Terrebonne Bay | Terrebonne | $22000000.00 |
| 435 | 1 | Nature Conservancy | TNC Oyster Reef in the Biloxi Marshes | St. Bernard | $40000000.00 |
| 436 | | Gulf Coast Preservation and Reclamation, Inc. | Saving the Gulf Coast one bale at a time | Coastwide | |
| 438 | | Restoration Systems | Jesuit Bend Coastal Wetland Site and Bank | Plaquemines | |
| 442 | 4 | United Country Louisiana Outdoor Properties | 8029 acres mitigation , marsh creation, coastal restoration | Cameron | |
| 443 | 2 | Restore the Earth Foundation | Gulf Saver Solutions® wetlands restoration initiative | Plaquemines | |
| 444 | CW | Beadfilters | Marine Finfish Hatchery for Stock Enhancement of Important Recreational Species Affected by the Oil Spill | | $50000000 |
| 445 | | University of Louisiana at Lafayette | Testing and Assessment of Archaeological Sites Impacted by the Deepwater BP Oil Spill | Jefferson/Plaquemines/St. Bernard/ Lafourche/Terrebonne | |
| 446 | | Nature Conservancy in Louisiana | Louisiana Reef Restoration | Cameron/Terrebonne/St. Bernard/ Plaquemines | |
| 447 | | Louisiana Sea Grant | Sustaining Louisiana's Seafood industry and preserving ecosystem services through Oyster Culture Budget: $15 million over 5 years | Jefferson/Plaquemines/Terrebonne/ St. Mary/Cameron | |
| 448 | | Bioremediation Inc. | Marshland Purification Project | Coastwide | |
| 449 | | University of Louisiana at Lafayette | Using Dredge Sediments to Remediate Oil-Contaminated Coastal Marshes | Coastwide | |
| 450 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Culch spreading to stabilize denuded muddy shoreline and near-shore areas and enhance oyster production. | St. Bernard | |
| 451 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Use induced high vertical profile oyster reefs to stabilize critical areas of shoreline erosion, and to enhance habitat conditions with living shoreline geometries | St. Bernard | |
| 452 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Submersible concrete barge surge breaker project along East Biloxi Marshes Shoreline Barrier Zone, Pilot | St. Bernard | |
| 453 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop an oyster hatchery and off-bottom growout technology | St. Bernard | |
| 454 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop a finfish hatchery and submersible concrete barge fingerling growout tanks. | St. Bernard | |
| 455 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop a marine technology program at Nunez Community College | St. Bernard | |
| 456 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop plan and design to upgrade infrastructure in working waterfront communities of eastern St. Bernard. | St. Bernard | |
| 457 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop plan and design for Violet safe harbor | St. Bernard | |
| 458 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Operating costs for Hopedale Oyster Reef and Fishing Grounds Restoration Center | St. Bernard | |
| 459 | 1 | Tangipahoa Parish Government | Lake Ponchartrain Shoreline Protection | Tangipahoa | |
| 460 | | SpecTIR LLC | Integrated Approach to Wetland Damage Assessment, Vegetation Monitoring, and Restoration Tracking in the Gulf of Mexico | Coastwide | |
| 461 | | United States Geological Survey | Response and recovery of the periphyton in the near-shore habitats of the Gulf of Mexico | Coastwide | |
| 462 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Restore bird islands (rookeries) with combination of cultch spreading and induced high vertical profile oyster reefs. | St. Bernard | |
| 463 | 2 | Randy Lanctot | Caminada Pass Bridge Fishing Pier Restoration | Jefferson | |
| 464 | | T/A Earth Creations | Mitigation of polluted waters through filtration by mussel clusters. | Coastwide | |
| 465 | | ECOCEAN | BioRestore® | Coastwide | |
| 466 | | Philip Chiocchio | Sodium Percarbonate dead zone oxygen replacement | Coastwide | |
| 467 | | Ernest Estevez | Giving Gulf Wetlands a Future | Coastwide | |
| 468 | | University of Houston Clear Lake | GOM Marine Sanctuaries | Coastwide | |
| 469 | | USFWS | Bird Friendly City Initiative | Coastwide | |
| 470 | 2 | Lafourche Parish Game and Fish Commission | Lake Fields Hyrologic Restoration | Lafourche | |
| 471 | | Bioremediation Inc. | Pure Beach Project | Coastwide | |
| 472 | | BioSonics, Inc | Quantitative Fish and habitat assessment and monitoring, using scientific acoustics | Coastwide | |
| 473 | | Joy Merino | SAV-E: SAV Establishment plan. | Coastwide | |
| 474 | 4 | Black Land Company LLC | Black Lake Marsh Creation | Calcasiue | |
| 475 | 3 | Pointe Au Chien Indian Tribe | Timbalier Bay Abandoned Canal Hurricane Protection Project | Lafourche/Terrebonne | |
| 476 | 2,3 | T. Baker Smith, LLC | Terrebonne / Lafourche Barrier Islands Segmented Breakwaters Concept | Lafourche | $240000000 |
| 478 | 2 | Greater Lafourche Port Commission | Fourchon Breakwaters Shoreline Protection | Lafourche | |
| 480 | 2 | South Lafourche Levee District | LL&E South Lafourche Marsh Restoration and Levee Protection | Lafourche | |
| 481 | 1 | City of Slidell | Bayou Pattasat Corridor Improvements | St Tammany | $17000000 |
| 482 | CW | LA Dept. Wildlife and Fisheries | EKOgrown® native trees for barrier islands restoration | Coastal | $10,000-$20,000/acre |
| 483 | 1 | St. Tammany Parish Government | Fritchie Marsh Terracing and Marsh Creation | St Tammany | $26000000 |
| 484 | 2/3 | South Lafourche Levee District | Twin Pipeline Canal Ridge Restoration and Fringe Marsh Creation | Lafourche, Terrebonne | |
| 485 | 1 | St. Tammany Parish Government | Bayou Bonfouca Marsh Creation | St Tammany | $22000000 |
| 486 | 1 | St. Tammany Parish Government | Northshore Marsh Creation | St Tammany | $16000000 |
| 487 | 1 | St. Tammany Parish Government | Unknown Pass to Rigolets | St Tammany | $12-24 Million |
| 488 | 1 | St. Tammany Parish Government | Northshore Marsh Shoreline Repair/Marsh Creation | St Tammany | $2200000 |
| 489 | 1 | St. Tammany Parish Government | Amite River Diversion | Livingston | |
| 490 | 1 | St. Tammany Parish Government | Convent Diversion | St James | |
| 491 | 1 | St. Tammany Parish Government | Mississippi River Diversion (Hope Canal Area) | St James/ St John | |
| 492 | CW | Aqua Green, LLC | Restoring Finfish of Importance to Louisiana Waters via Private Industry | Coastal | |
| 493 | 2 | Private Landwoner | PPL20 - Lake Lery Marsh Restoration project | St Bernard | $20-25 Million |
| 494 | 2 | E Sciences, Inc | Bayou Chevreuil LA NRDA Response Site | Lafourche/ St James | |
| 495 | 1 | The Conservation Fund | Lake Maurepas Land Protection Effort | Livingston/ Tangipahoa | |
| 496 | 1 | The Conservation Fund | Lake Maurepas Land Protection Effort | Livingston, Tangipahoa | |
| 497 | 3/6 | The Conservation Fund | Atchafalaya Basin Protection Effort | Iberville, Pointe Coupee, St Martin | |
| 498 | 3, 6 | The Conservation Fund | Atchafalaya Basin Protection Effort | Iberville, Pointe Coupee, St Martin | |
| 499 | CW | AgSource LLC | ASEG | Coastal | |
| 500 | 2 | Grand Isle Port Commission | Grand Isle and Vicinity barrier Islands Protection and Enhancement Project | Jefferson, Lafourche | |
| 501 | 1 | Lake Pontchartrain Basin Foundation | Enhancement of shoreline, SAV and shoal habitats along the Little Woods area of Lake Pontchartrain (Southeast area) | Orleans | $ 1 Million |
| 502 | 1 | Lake Pontchartrain Basin Foundation | South shore Wetlands Restoration and Protection Jefferson Parish, Louisiana (southern area) | Jefferson | $960000 |
| 503 | 1 | Lake Pontchartrain Basin Foundation | Shoreline canal restoration Madisonville to Manchac (northwest area) | St Tammany, Tangipahoa | $950000 |
| 504 | 2 | Blue Planet Water Solutions | Bay Jimmy Marsh Restoration | Plaquemines | |
| 505 | CW | BioWorld Products Inc | BioWorld Louisiana Gulf Coast Bioremediation Project | Coastal | $2K-6K per ac |
| 506 | 1 | Robins Capital LLC. / DPed INC LLC / Praiswater LLC. | Oyster Rejuvenation | St Bernard | |
| 507 | 4 | Cameron Parish Police Jury | Calcasieu Lake Shoreline Restoration 3.2 Miles (Sabine NWF) | Cameron | $6.2 Million |
| 508 | 4 | Cameron Parish Police Jury | Calcasieu Lake Shoreline Boundary Restoration 5.2 Miles (Sabine NWF) | Cameron | $10.04 Million |
| 509 | 4 | Cameron Parish Police Jury | Grand Lake Shoreline Restoration (Laccassine NWR) | Cameron | $4.69 Million |
| 510 | 4 | Cameron Parish Police Jury | Prescribed Fire (Laccassine NWR) | Cameron | $69000 |
| 511 | 4 | Cameron Parish Police Jury | Prescribed Fire (Sabine NWR) | Cameron | $66000 |
| 512 | 4 | Cameron Parish Police Jury | Shoreline Stabilization (Shell Keys NWR) | Cameron | $15 Million |
| 513 | 4 | Cameron Parish Police Jury | Restoration of Coastal Wetlands (Sabine NWR Units 2 and 4) | Cameron | $2.2 Million |
| 514 | 4 | Cameron Parish Police Jury | Prescribed Fire (Cameron Prairie NWR) | Cameron | $28000 |
| 515 | 4 | Cameron Parish Police Jury | Willow Cutoff Wetland Restoration (Laccassine NWR) | Cameron | $536250 |
| 516 | 4 | Cameron Parish Police Jury | Restore South Levee of Laccassine Pool (Laccassine NWR) | Cameron | $14.8 Million |
| 517 | 4 | Cameron Parish Police Jury | Feral Hog Removal (Sabine NWR) | Cameron | $50K - $69K |
| 518 | 2 | Jefferson Parish | Bayside Segmented Breakwaters at Grand Isle | Jefferson | $3,300,000 |
| 534 | | Coastal Environments Inc for St Bernard Parish | Keelboat Island Living Shoreline Stabilization | St Bernard | $700000 |
| 536 | | Southern Shrimp Alliance | Deployment of New Turtle Excluder Devices in Shrimp Fisheries | | $10800000 |
| 537 | | LaCoastPost.com | Acquisition of at-risk landscape and developing independent science-based priority measures for America's Delta. | | $100000000 |
| 539 | 1 | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Submersible Concrete Barge Surge Breaker along East Biloxi Marshes Shoreline Barrier Zone, Pilot | | $4500000 |
| 540 | | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop a finfish hatchery and submersible concrete barge fingerling growout tanks. | | $2000000 |
| 541 | | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop plan and design to upgrade infrastructure in working waterfront communities of eastern St. Bernard. | | $500000 |
| 542 | | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Operating costs for Hopedale Oyster Reef and Fishing Grounds Restoration Center | St Bernard | $200000 |
| 543 | | The Conservation Fund | Maurepas Swamp/ Joyce WMA - Lake Maurepas Land Protection Effort | Livingston | |
| 544 | | Bioremediation Inc. | Marshland Purification Project | St Bernard | |
| 546 | | Beadfilters | Marine Finfish Hatchery for Stock Enhancement of Imporant Recreational Species Affected by the Oil Spill | | $50000000 |
| 547 | | United States Geological Survey | Response and recovery of the periphyton in the near-shore habitats of the Gulf of Mexico | | $850000 |
| 548 | | University of Louisiana at Lafayette | Testing and Assessment of Archaeological Sites Impacted by the Deepwater BP Oil Spill | | $180000 |
| 549 | | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Culch spreading to stabilize denuded muddy shoreline and near-shore areas and enhance oyster production. | St Bernard | $4000000 |
| 551 | | Coastal Environments, Inc. on behalf of St. Bernard Parish Government | Develop a marine technology program at Nunez Community College | | $2500000 |
| 554 | 2 | Plaquemines Parish Government | Parish Shoreline Stabilization | Plaquemines | $58,000,000 |
| 558 | 1, 2, 3, 4 | Marine Gardens LLC | Commercial based restoration of finfish of importance to coastal Louisiana | | $3,000,000 |
| 560 | 3 | Wetlands and Wildlife Management Co. | Marsh Restoration Project at Point Au Fer | Terrebonne | $20 million |
| 561 | 3 | Wetlands and Wildlife Management Co. | Point Au Fer Island Burkes Bayou Breach | Terrebonne | $1,600,000 |
| 620 | 4, 7 | Ecosystem Investment Partners | Calcasieu Pine Savanna | | $6,800,000 |
| 621 | 2, 3 | United Houma Nation | United Houma Nation Culture Center | Terrebonne | $4.5M to 7MAdmi |
| 622 | 1 | Ecosystem Investment Partners | Chef Menteur Restoration | Orleans | |